DPW-24227- Rebid: ISU: Meridian Install 2nd Cooling Tower Connection

Contractor is to install a 2nd fluid cooler on the heat pump loop new pipping & electrical power & Controls.

Status

Accepting Bids

Prebid Date 9/25/25 10:00am
Bid Date 10/7/25 10:30am

Company & Contacts

Idaho Division of Public Works
Kelly Berard  
208-332-1900

Location

Meridian, Idaho

Base Bid: Contractor is to install a 2nd fluid cooler on the heat pump loop, new piping, electrical

power and controls as required for the installation. The base bid will include the installation of a

new concrete pad to mount the fluid cooler on and the chemical feed system for the fluid cooler.

Bid Alternate #1: Contractor is to build a masonry enclosure around the new cooling tower per

the architectural and structural drawings included.

Estimated Cost: $534,750.00